How long will Lower Hutt city be disrupted while construction goes on?

We anticipate enabling works will commence late 2022, with construction proper following along closely after that (in 2023) - the majority being completed by the end of 2027. 

It’ll be done in stages:

  • Removal of vegetation/buildings and dwellings, relocation of services and site investigations.
  • Sites, access, and haul roads established, trial embankments/erosion and sediment control devices installed.
  • Main construction works - river channel works; access to specific sites (culverting and access bridges); ground improvements; earthworks; building new structures; pavements and surfacing; completion works (traffic services, landscaping).